Connect via MCP →

Enter Calculation

Formula

Show calculation steps (2)
  1. Standard Deviation (SD)

    Standard Deviation (SD): PERT Estimate Calculator

    Spread of the estimate based on the range P minus O

  2. Variance

    Variance: PERT Estimate Calculator

    Square of the standard deviation

Advertisement

Results

Expected Time (TE)
8
PERT weighted estimate
Standard Deviation (SD) 2
Variance 4

What Is the PERT Estimate Calculator?

The PERT (Program Evaluation and Review Technique) calculator turns three time guesses into a single, statistically-weighted estimate. Instead of relying on one number, you provide an Optimistic (O), Most Likely (M), and Pessimistic (P) duration. The tool returns the Expected Time (TE), the Standard Deviation (SD), and the Variance — giving you both a realistic estimate and a measure of its uncertainty. It works for any unit of time (hours, days, weeks) as long as you stay consistent.

How to Use It

Enter your three estimates for a task. The Optimistic value is the best-case duration if everything goes smoothly, the Most Likely is your realistic call, and the Pessimistic is the worst-case scenario. Press calculate to see the weighted expected time and how much it might vary.

The Formula Explained

PERT uses a beta distribution and weights the most likely estimate four times more heavily than the extremes:

$$TE = \frac{\text{Optimistic (O)} + 4 \times \text{Most Likely (M)} + \text{Pessimistic (P)}}{6}$$

The spread of possible outcomes is captured by the standard deviation:

$$SD = \frac{\text{Pessimistic (P)} - \text{Optimistic (O)}}{6}$$

Variance is simply \(SD^{2}\). A large standard deviation signals a risky task that deserves a buffer.

Advertisement
Six-part weighting diagram showing O plus four times M plus P divided by six
The formula divides the weighted sum (O + 4M + P) by six total weights.
Number line with optimistic, most likely, pessimistic points under a skewed distribution curve
PERT weights the most likely value four times to find the expected time TE between O, M, and P.

Worked Example

Suppose a feature takes 4 days optimistically, 7 days most likely, and 16 days pessimistically. Then $$TE = \frac{4 + 4 \times 7 + 16}{6} = \frac{4 + 28 + 16}{6} = \frac{48}{6} = 8 \text{ days}.$$ $$SD = \frac{16 - 4}{6} = \frac{12}{6} = 2 \text{ days},$$ so variance \(= 4\). You would plan for 8 days, knowing roughly ±2 days of uncertainty.

FAQ

Why is M multiplied by 4? The beta distribution assumes the most likely value dominates, so it carries four-sixths of the weight while O and P share the rest.

What units should I use? Any consistent time unit — hours, days, or weeks. The output uses the same unit as your inputs.

How do I combine many tasks? Sum the TE values for the total expected duration, and sum the individual variances (not standard deviations) before taking the square root for the overall SD.

Last updated: